Environmental Review Schedule for Spire STL Pipeline, LLC’s (Spire) Proposed Pipeline Project in Missouri and Illinois

BackgroundFERC announced an environmental review schedule for Spire STL Pipeline, LLC’s (Spire) Proposed Pipeline Project in Missouri and Illinois. FERC intends to issue an EA for the project by September 29, 2017 and a final authorization by December 28, 2017. The proposed project includes: (1) approximately 65 miles of new 24-inch-diameter pipeline in Scott, Greene, and Jersey Counties, Illinois and St. Charles and St. Louis Counties, Missouri, (2) a new meter station in Scott County, Illinois, (3) two new meter stations in St Louis County, Missouri, and (4) additional piping and pigging facilities at each of the three meter stations.

Dates:

  • FERC intends to issue an EA for the project by September 29, 2017 and a final authorization by December 28, 2017.